MAR ORGANICA · INTERNAL WIP

CPSHP 01Z0 Command Center

Rev. 3 control basis
Ask the project

Search the schedule, money, façade plan or final proposal.

Day 0 through finish

Interactive Daily Project Manager

Choose any date from preconstruction through the modeled payment/claims-preservation horizon. The exact crew IDs, superintendent, work blocks, JHAs, documents, cost, CPM window and back-office actions update together.

Named crew & roles

Exact-day work packet

    JHA / documents / office routing

    Device-local working record

    Daily update

    Editable local employee system

    Employee Database, Timecard & Paystub Worksheet

    Kostas is the planned project superintendent. Placeholder employee IDs persist across consecutive days until actual names are entered. Rates are active internal inputs based on your confirmation; verify the project determination and fringe treatment before certified payroll.

    Weekly payroll is the control default.A compliant biweekly payroll may be possible if California payday timing and the executed subcontract allow it, but crew/classification hours and certified-payroll records remain tracked by workweek.
    IDEmployee / placeholderRoleClassificationEmployerCash rateFringeStatusAction

    Mar Organica itemized wage statement worksheet

    Full façade clean · base plus change control

    Suspended-Access Execution Plan

    Two stages, approximately 26 drops and a 48,700-SF field-verification basis. The plan below is the handoff sequence from survey through off-rent; every first-use gate remains a hard hold.

    Party split / RACI

    First-use hold points

    Job-specific activity hazard analyses

    30-Activity JHA / AHA Library

    Every scheduled work type maps to a job JHA with hazards, controls, PPE, prestart requirements, competent-person responsibility, stop-work triggers and evidence.

    Nothing measured = nothing assumed

    440-Point Preconstruction Survey & Evidence Matrix

    Includes 260 façade-drop points, 120 interior level points and project-wide roof/access, logistics, pressure-wash and contract confirmations. Status and notes save to this device.

    0 / 440verified
    DoneID / zoneTypeExact requirementUnit / evidenceField note / link
    Quotes, qualification and decision record

    Potential Vendor & Labor Source Database

    Nineteen Central Coast leads are preloaded. No vendor is awarded. Save proposal amount/date/link, notes and qualification checklist on this device.

    Internal earned-value planning

    Progress Payment & Milestone Lab

    Model a proposal-based pay request by cutoff date. This is a planning suggestion—not a guarantee of approval—and must be reconciled to WT’s executed pay-app and retention terms.

    Approved changes are shown separately. Do not add a theoretical façade change to an external pay request.
    DateMilestoneCumulative earnedIncrementInternal suggestion
    Every bar is clickable

    Daily, Weekly & 30-Day Histograms

    Switch the measure and time window. Selecting a bar synchronizes the Daily Project Manager above.

    Weekly payroll cash

    Cumulative spend vs. target cost cap

    Theoretical schedule scenarios

    S0 is the internal B0. S1-S7 are planning tests only and do not authorize acceleration, rental commitments or change work.

    Primavera-style CPM control

    Early / Late Dates, Float & Logic

    The B0 register uses 26 activities, 28 FS/0 ties and a five-day calendar. Use the filters to isolate critical work or the activities touching the selected day.

    ID / WBSActivityESEFLSLFFloatLHPred → Succ
    Separate project · separate cost codes

    Façade Change-Order Project Manager

    The base promise remains the entire façade, two swing stages and 180 cleaning labor-hours. A change request needs a changed fact or written direction—not merely a base overrun.

    Base façade allocation$27,030
    Base labor control180 LH
    Rate controlUser confirmed same · verify CPR/billing basis
    Notice disciplineSame-day event record

    Decision gates

    PM playbook

    Open the 33-activity façade CO schedule
    IDActivityESEFOwnerDeliverable / Gate
    Quotes, POs, rentals & cash

    Materials and Rental Control

    Sixteen lines remain unpriced or unsupported. Replace planning placeholders before commitment.

    IDClassItem / scopeDatesPlanned totalVendor / statusRule
    Every dollar reconciles

    Contract, Cost Code, Overhead & Profit Control

    The internal plan reconciles exactly to $182,100. Edit planning buckets to actual commitments; this is not an external schedule of values unless WT accepts it.

    $182,100of $182,100 allocated
    CodeInternal bucketAmountBasis
    Project survives any handoff

    Back-Office, Filing, Payroll & Claims-Preservation Matrix

    What happens every day, week, pay cycle, quarter, change event and closeout—who owns it, where it goes and when it is due.

    FrequencyOwnerRequired recordDestinationDue

    Routing register

    Public-works claims-preservation calendar

    Open current compliance source register
    Whiting-Turner controlled intake

    WT SharePoint Connection & Authority Register

    The site can store the SharePoint address and intake status locally. Actual document access requires the exact WT URL and your private Microsoft sign-in; credentials never belong in this HTML.

    Not verified

    Required authoritative intake

    Full internal knowledge base

    Searchable Manuals, Safety Books, Workbooks & Final Proposal

    Sixteen source files—including the full expert manual, bilingual manual, safety compendium, AHA/release/payment manual, field walkthroughs and the explicitly excluded 91-page subcontract draft—are indexed below. Final Proposal Rev. 3 remains the commercial control.

    Download original PDF
    Controls$182,100 lump sum and Exhibit H allocations
    ScheduleSeptember 14 first mobilization
    ExcludedSubcontract DRAFT as final authority
    
          
    View the original one-page proposal PDF inside this HTML