Search the schedule, money, façade plan or final proposal.
Interactive Daily Project Manager
Choose any date from preconstruction through the modeled payment/claims-preservation horizon. The exact crew IDs, superintendent, work blocks, JHAs, documents, cost, CPM window and back-office actions update together.
Exact-day work packet
JHA / documents / office routing
Daily update
Employee Database, Timecard & Paystub Worksheet
Kostas is the planned project superintendent. Placeholder employee IDs persist across consecutive days until actual names are entered. Rates are active internal inputs based on your confirmation; verify the project determination and fringe treatment before certified payroll.
| ID | Employee / placeholder | Role | Classification | Employer | Cash rate | Fringe | Status | Action |
|---|
Suspended-Access Execution Plan
Two stages, approximately 26 drops and a 48,700-SF field-verification basis. The plan below is the handoff sequence from survey through off-rent; every first-use gate remains a hard hold.
Party split / RACI
First-use hold points
30-Activity JHA / AHA Library
Every scheduled work type maps to a job JHA with hazards, controls, PPE, prestart requirements, competent-person responsibility, stop-work triggers and evidence.
440-Point Preconstruction Survey & Evidence Matrix
Includes 260 façade-drop points, 120 interior level points and project-wide roof/access, logistics, pressure-wash and contract confirmations. Status and notes save to this device.
| Done | ID / zone | Type | Exact requirement | Unit / evidence | Field note / link |
|---|
Potential Vendor & Labor Source Database
Nineteen Central Coast leads are preloaded. No vendor is awarded. Save proposal amount/date/link, notes and qualification checklist on this device.
Progress Payment & Milestone Lab
Model a proposal-based pay request by cutoff date. This is a planning suggestion—not a guarantee of approval—and must be reconciled to WT’s executed pay-app and retention terms.
| Date | Milestone | Cumulative earned | Increment | Internal suggestion |
|---|
Daily, Weekly & 30-Day Histograms
Switch the measure and time window. Selecting a bar synchronizes the Daily Project Manager above.
Weekly payroll cash
Cumulative spend vs. target cost cap
Theoretical schedule scenarios
S0 is the internal B0. S1-S7 are planning tests only and do not authorize acceleration, rental commitments or change work.
Early / Late Dates, Float & Logic
The B0 register uses 26 activities, 28 FS/0 ties and a five-day calendar. Use the filters to isolate critical work or the activities touching the selected day.
| ID / WBS | Activity | ES | EF | LS | LF | Float | LH | Pred → Succ |
|---|
Façade Change-Order Project Manager
The base promise remains the entire façade, two swing stages and 180 cleaning labor-hours. A change request needs a changed fact or written direction—not merely a base overrun.
Decision gates
PM playbook
Open the 33-activity façade CO schedule
| ID | Activity | ES | EF | Owner | Deliverable / Gate |
|---|
Materials and Rental Control
Sixteen lines remain unpriced or unsupported. Replace planning placeholders before commitment.
| ID | Class | Item / scope | Dates | Planned total | Vendor / status | Rule |
|---|
Contract, Cost Code, Overhead & Profit Control
The internal plan reconciles exactly to $182,100. Edit planning buckets to actual commitments; this is not an external schedule of values unless WT accepts it.
| Code | Internal bucket | Amount | Basis |
|---|
Back-Office, Filing, Payroll & Claims-Preservation Matrix
What happens every day, week, pay cycle, quarter, change event and closeout—who owns it, where it goes and when it is due.
| Frequency | Owner | Required record | Destination | Due |
|---|
Routing register
Public-works claims-preservation calendar
Open current compliance source register
Searchable Manuals, Safety Books, Workbooks & Final Proposal
Sixteen source files—including the full expert manual, bilingual manual, safety compendium, AHA/release/payment manual, field walkthroughs and the explicitly excluded 91-page subcontract draft—are indexed below. Final Proposal Rev. 3 remains the commercial control.